How to write a heat pump quote: survey data, line items and terms
What to check on site, which line items to list and what to exclude in a heat pump quote. A practical guide with sample lines and terms.
A heat pump quote is not a boiler swap. The right unit depends on the building, the emitters and the hot water demand. One missed detail on the survey can turn into extra cost on install day or an unhappy customer in January. A good quote puts these risks in writing from the start.
Want to try it right away? Our free quote generator lets you create a quote online and download it as a PDF, no sign-up needed.
Site data to collect first
Gather this before you price anything. It sizes the system and gives you the reasons behind your recommendation.
- Heat loss calculation, or at least floor area, insulation level and current fuel use.
- Emitters: radiators, underfloor heating or a mix.
- Required flow temperature; older radiators may need a higher one or upsizing.
- Hot water demand: number of occupants, bathrooms, existing cylinder.
- Electrical supply: main fuse rating, consumer unit location, cable route.
- A suitable spot for the outdoor unit and distance to neighbouring properties.
Line items
Put each component on its own line. The customer sees what they are paying for, and when a revision comes in you know which line changed.
- Air-to-water heat pump outdoor unit, 8 kW
- Indoor unit / hydraulic module
- Hot water cylinder, 200 L
- Buffer tank, 50 L
- Room thermostat and controller
- Electrical connection and isolator
- Pipework, valves and magnetic filter
- Commissioning and customer handover
What is included and what is not
Most disputes start with exclusions. List them under their own heading: radiator upgrades, making good after drilling, concrete base, supply upgrades by the network operator, removal of the old boiler. Add one line: "Any work not listed above is excluded."
Noise and placement notes
Customers often think about the outdoor unit only after it is on the wall. Add a short note: where it will sit, distance to bedroom windows and the boundary, anti-vibration feet and an acoustic screen if needed. If planning consent or landlord approval is required, state that it is the customer's responsibility.
Grants and subsidies
Support schemes for heat pumps vary by region. Do not promise any amount in the quote; a line such as "We recommend checking local grant schemes before ordering" is enough. If you will help with the paperwork, list it as a separate service line.
Validity and payment terms
- This quote is valid for 15 days.
- Payment: 50% on order, 40% on delivery of equipment, 10% on commissioning.
- Installation time: 3 working days from delivery to site.
- Warranty: manufacturer's warranty from the commissioning date.
Final check
Before sending, read the quote as the customer would: does the output match the heat loss, is the hot water capacity enough, are the exclusions clear? Then set a follow-up date. Heat pump decisions are usually talked over at home, so a short call a few days later clears up the questions. For a small firm like Hartley Heating, that call is often what wins the job.